Commissioning works of the Complex for the injection of pulverized coal for the Blast furnace No. 9 of PJSC “AMKR” have been completed
Dec 20, 2015Implementation of a pulverized coal automation system based on PLC equipment from Allen-Bradley, using field equipment from SIEMENS, Emerson, VEGA, etc. In […]
Automation of the complex for the injection of pulverized coal into the Blast furnace No. 9
Dec 15, 2015As part of the implementation, the following scope of work was performed: In regard to the transportation and accumulation of coal dust: […]
Local control system of pump units with adjustable wet clutches
Sep 15, 2015The automation of 4 feed water pumps and large network pumps was implemented for Kiev city pumping stations.
The frequency control of the drives of the pulverized coal feeders of the power unit No. 3 has been implemented at the Zaporozhskaya TPP.
Nov 14, 2014The specialists of our company have successfully implemented a project to modernize pulverized coal feeders of the power unit No.3 (325 MW) […]
Start of pumping equipment automation at Kiev CHP
Feb 14, 2014A contract has been signed for the implementation of automation systems for pumping units at Kiev CHP, PJSC “Kyivenergo”. As part of […]
The control system for the turbine and the main parameters of the boiler of the power unit No. 12 at the Starobeshevskaya TPP, PJSC Donbassenergo was implemented
Dec 22, 2013The turbine control system K-200-130 and the regulation of the main parameters of the boiler TП-100 of the power unit st. No. […]